Which of the following is NOT one of the correct steps in using a PERT

QUESTION

Which of the following is NOT one of the correct steps in using a PERT chart in a production process?

A) Identify the tasks.
B) Arrange the tasks in the order in which they must take place.
C) Estimate the time needed to complete each task.
D) Diagram the task sequences and times.
E) Compute the sequence of tasks that takes the least time to complete to learn how quickly you can complete the project.

 

ANSWER

Answer: E
Explanation: E) You need to compute the critical path. In a PERT chart, the critical path is the sequence of tasks that takes the longest time to complete. The critical path will tell you the time expected to complete the project.