QUESTION
Which of the following is NOT a reason PERT charts are used?
A) to analyze either goods production or a service
B) to analyze the tasks involved in completing a project
C) to determine the minimum time needed to complete each task
D) to determine what tasks are needed to complete a project
E) to determine the total time for a project
ANSWER
Answer: D
Explanation: D) Managers use PERT charts to analyze the tasks involved in completing a project and estimate the minimum time needed to complete each task, as well as the total time for the project. PERT charts can be used for projects related to both goods and services.