the table below to develop a precedence diagram

QUESTION

Project ManagementProject SchedulingDevelop and build the following project schedule.1. Use the table below to develop a precedence diagram2. Identify the early start and early finish for each task3. Identify the late start and late finish for each task4. Identify the float in each task5. Identify any tasks that have free floatActivity – Immediate Preceding Activity – Durationa. Excavate — 5b. Foundation a 2c. Frame b 12d. Electric c 9e. Roof c 5f. Brick c 8g. Finish interior d 10h. Finish exterior d 7i. Landscape h 5All five activities must be included in the answer.MS Project (or any scheduling software) is not to be used. Use post-its, PPT, Excel, Word, Visio, or any drawing type software.

 

ANSWER: