The discount rate assigned to an individual project should be based on:
A) the firm’s weighted average cost of capital.
B) the actual sources of funding used for the project.
C) an average of the firm’s overall cost of capital for the past five years.
D) the current risk level of the overall firm.
E) the risk level of the project itself.
ANSWER
E