One problem with a cost plus incentive fee procurement contract is ___

One problem with a cost plus incentive fee procurement contract is _____.

a. it requires clearly defined output that is not really malleable
b. it almost always leads to higher costs
c. firms have a strong incentive to invest in the most expensive technology to complete the project
d. firms have an incentive to misrepresent final costs

 

ANSWER

d

 