QUESTION
In the Monte Carlo technique, what is the criticality index?a. The number of days the project will be late divided by the project durationb. The percent of time a given activity will be on the critical pathc. The percent of time an activity will be late d. The sum of the duration of the critical path activities divided by the project expected value for duration
Answer : b. The percent of time a given activity will be on the critical path Explanation : Criticality index means the chance that a particular
ty will be on the critical path and is more likely to cause delay as it exists on the critical path .