QUESTION
Scaffolding is to be constructed on all faces of a six-story building in order for major masonry rehabilitation work to be performed. The exposed surface area of the exterior walls of the building has been estimated to be 423,000 sq. ft. Historical records of the company show that for this simple type of structure, the production rate for erecting scaffolding is 0.002 hours per square foot of building surface area. If 10 workers (working 8 hours days) are assigned to do the entire scaffolding erection, answer the following question?How many worker hours are required to erect the scaffolding?How many hours are required per worker?What duration (in working days) should be used for this activity? Round up your answer to the nearest whole integer day.