BSOP 209 Operations Analysis Week 3 Assignment and Case Study Devry

QUESTION

BSOP 209 Operations AnalysisWeek 3Week 3 Assignment:S7.17Markland Manufacturing intends to increase capacity by overcoming a bottleneck operation by adding new equipment. Two vendors have presented proposals. The fixed costs for proposal A are $50,000, and for proposal B, $70,000. The variable cost for A is $12.00, and for B, $10.00. The revenue generated by each unit is $20.00.a) What is the break-even point in units for proposal A?Discussion Questions (Case Study)1. Develop a forecasting model, justifying its selection over other techniques, and project attendance through 2011.2. What revenues are to be expected in 2010 and 2011?3. Discuss the school’s options

 

ANSWER: