QUESTION
Based on the description above, during the planning process the project managers of the Pest Eradication Device most likely failed to adequately address all of the following issues EXCEPT which one?
A) Will the Pest Eradication Device function in the way that customers demand?
B) Is there any demand in the market for a remote-controlled pest-killing device?
C) Are customers likely to understand how to use the device?
D) What should ACME do to help customers who are unable to understand how to use the device?
E) Is there enough time to plan for and carry out the project?
ANSWER
Answer: B
Explanation: B) The wrong choices cover the known faults of the project. It was late (Choice E). It didn’t function in desert conditions (Choice A). The instructions (Choice C) were bad, and customer support was nonexistent (Choice D). However, as far as we know, the essential idea was a good one, and so Choice B doesn’t point out a problem.