Which bits of information go onto a Gantt chart? A) task, start date,

QUESTION

Which bits of information go onto a Gantt chart?

A) task, start date, end date
B) task, start date, end date, employees responsible
C) time, tasks, and employees responsible
D) tasks and employees responsible
E) time and tasks

 

ANSWER

Answer: E
Explanation: E) In creating a Gantt chart, you express the time across the top and the tasks down along the left side.