QUESTION
Which bits of information go onto a Gantt chart?
A) task, start date, end date
B) task, start date, end date, employees responsible
C) time, tasks, and employees responsible
D) tasks and employees responsible
E) time and tasks
ANSWER
Answer: E
Explanation: E) In creating a Gantt chart, you express the time across the top and the tasks down along the left side.