QUESTION
Which of the following statements about project standing alonerisk is true?a. It ignores the fact that much of the risk of a project willbe diversified away as the project is combined with the firmsother projects.b. It ignores the cash flows that are associated with aproject that occur beyond the p
a. It ignores the fact that much of the risk of aproject will be diversified away as the project is combined withthe firms other projects. b. It ignores the cash flows that are associated with aproject that
ccur beyond the payback period.c. It takes into consideration the effects of diversificationof the firms shareholders.d. None of the above
ANSWER: